Installing Bermudagrass Sod: Step-by-Step Guide

The process mirrors fescue sod installation but timing differs (bermudagrass sod is best laid in early summer).

Site Preparation

  1. Kill weeds with non-selective herbicide 2 weeks prior.
  2. Till 6 inches deep; incorporate lime/fertilizer per soil test (1-800-ASKUGA-1). Without test: 50 lbs lime + 20 lbs 5-10-15/1,000 sq ft + 1 inch compost.
  3. Rake smooth; remove debris.
  4. Roll with water-filled roller to reveal low spots; fill them.
  5. Critical: Irrigate ¼–½ inch night before. Soil must be damp.

Laying Sod

  • Start on longest straight edge; butt pieces tightly.
  • Stagger seams (brick pattern).
  • Trim with hatchet/sharp shovel.
  • Roll entire area for root-to-soil contact.
  • Water thoroughly (see schedule).

Watering New Sod

  • Day 1: 1 inch immediately.
  • Daily: keep top 1 inch moist until rooted.
  • Days 10–18: ¼ inch every 3rd day (9 days).
  • Days 19–28: ½ inch every 5th day (10 days).
  • Thereafter: 1 inch/week. Adjust for rain.

Use judgment: amounts vary by season. Check penetration with trowel. Clay: split sessions if runoff. Sandy: split weekly inch into two ½-inch apps 3 days apart.

General Watering

Morning before noon. Measure output with 6 cups. Check georgiadrought.com for restrictions.